Silver Ridge Court
Back to homepagePorch Finish: All unit porches are inspected every Fall. Necessary repairs are made at that time, and porches with new wood or those needing re-staining are stained the following Summer.
| Address | Painting | Gutter Cleaning* | Roof Inspection |
|---|---|---|---|
| 35040 | 2026 | Jun; Nov | 2023 |
| 35050 | 2026 | Jun; Nov | 2023 |
| 35055 | 2026 | Nov | 2022 |
| 35060 | 2026 | Jun; Nov | 2023 |
| 35065 | 2026 | Nov | 2025 |
| 35070 | 2026 | Jun; Nov | 2023 |
| 35075 | 2026 | Nov | 2025 |
| 35085 | 2026 | Nov | 2025 |
*Apr=April; Jun=June; Aug=August; Nov=November